  3. How to calculate cut and fill from contour lines on PDF plans

How to calculate cut and fill from contour lines on PDF plans

The Excav team · Updated

A grading plan tells you two things about every spot on the site: where the ground is now (the existing contours, usually dashed) and where it needs to end up (the proposed contours and spot grades, usually solid). Cut and fill is the difference between the two, added up over the whole area.

This guide walks through how to do that from the PDF set you get at bid time, without CAD files.

What you need from the plans

  • The existing topography. Existing contours and spot elevations, usually on the existing conditions or grading sheet.
  • The proposed grading. Proposed contours, spot grades, top and bottom of curb, finished floor elevations.
  • The scale and the contour interval. A 1-foot interval and a 2-foot interval look the same on paper. Read the legend before you start.
  • The typical sections. Pavement and road sections, so you know how far below finished grade the dirt work really stops.

Step 1: Calibrate the sheet

Measure a known dimension on the sheet (a scale bar or a dimensioned line) and set the scale before you measure anything. Detail sheets in the same set are often at a different scale from the plan sheets.

Step 2: Pick a method

There are three common ways to turn contours into yards. They all do the same thing: compare proposed to existing over an area, then add it up.

The grid method

Lay a grid over the site. At each cell, figure the depth of cut or fill (proposed minus existing, averaged over the cell), multiply by the cell's area, and add up the cells.

cell volume (CF) = cell area (SF) × average depth (FT)
cut and fill (CY) = total CF ÷ 27

Smaller cells follow the ground more closely. This is the method a computer is best at, because it can use thousands of small cells instead of a few dozen big ones.

Cross sections (average end area)

Cut sections across the work at regular stations, measure the cut and fill area on each section, and average each pair of neighbouring sections:

volume (CY) = (area 1 + area 2) ÷ 2 × distance between them ÷ 27

This is the usual way to figure roads and channels, because the plans often include the profile and typical section already.

Contour areas (horizontal slices)

Measure the area enclosed by each contour, then treat the space between two contours as a slice: the average of the two areas times the contour interval. This works well for ponds and stockpiles.

Worked example: a small pad by the grid method

Made-up numbers. A pad area is split into six cells, each 50 ft × 50 ft (2,500 SF). The average depth in each cell is proposed minus existing:

Cell Average depth (ft) Volume (CF)
1 −2.0 (cut) 5,000
2 −1.2 (cut) 3,000
3 −0.4 (cut) 1,000
4 +0.6 (fill) 1,500
5 +1.4 (fill) 3,500
6 +2.2 (fill) 5,500
Cut  = 9,000 CF  ÷ 27 = 333.3 CY (bank)
Fill = 10,500 CF ÷ 27 = 388.9 CY (compacted)

The cut and the fill aren't the same kind of yard yet. Cut comes out of the ground as bank yards. Fill goes back in as compacted yards, and compacted dirt takes up less room than it did in the bank. With a shrink factor of 1.15 (1.15 bank yards to make one compacted yard):

Fill needs, as bank  388.9 × 1.15 = 447.2 CY
Cut available, bank                 333.3 CY
Import, bank         447.2 − 333.3 = 113.9 CY

So the site is short about 114 bank yards, before any topsoil strip or pavement section is taken off. More on factors in shrink and swell factors explained.

Worked example: two road sections

Made-up numbers. At station 1+00 the cut area on the cross section is 120 SF. At 1+50 it's 180 SF.

(120 + 180) ÷ 2 × 50 ÷ 27 = 277.8 CY of cut between the two stations

Mistakes that throw the total off

  • Reading the wrong contour interval. If you count contours to get elevations between the labeled ones, a 2-foot interval read as 1 foot halves every depth you figure from them.
  • Forgetting the pavement section. Proposed contours show finished grade. Where there's asphalt, base and pit run, the dirt work stops at subgrade, a foot or two lower. See how to take off a pavement section.
  • Carrying the grading too far. Past the last proposed contour, the design ties back into existing ground. Extending the last proposed line across the site invents cut or fill nobody drew.
  • Comparing bank to compacted. Cut and fill only balance after converting with your shrink factor.
  • Skipping the topsoil strip. Stripped topsoil usually can't go back in as structural fill. Take it off first.
  • Trusting a printed total without checking what's in it. An engineer's earthwork number may or may not include pavement sections, stripping or shrink. Ask, or figure your own.

Doing it from the PDF

By hand, the grid method on a real site means hundreds of cells and a long night. The same method is what earthwork software does in the background: you trace the existing and proposed lines on the sheet, it builds both surfaces and compares them cell by cell. Whichever way you do it, keep the factors and the limits of grading visible, so anyone checking the bid can see where every yard came from.