Shrink and swell factors: bank, loose and compacted yards explained

The Excav team · Updated

A cubic yard of dirt isn't always a cubic yard. The same material takes up a different amount of room in the ground, in the truck and in the fill. Getting that wrong is one of the fastest ways to miss import or export on a bid.

Three states of the same dirt

  • Bank yards (BCY): the material as it sits in the ground, undisturbed. Cut is measured in bank yards.
  • Loose yards (LCY): the same material after it's dug up. It breaks apart, gets air in it and takes up more room. Trucks haul loose yards.
  • Compacted yards (CCY): the material after it's placed and compacted in a fill. Usually tighter than it was in the bank. Fill is measured in compacted yards.

Swell: bank to loose

Swell is how much the material grows when it's dug.

loose yards = bank yards × swell factor
swell factor 1.25 = 25% swell

Shrink: bank to compacted

Shrink is how much smaller the material ends up after it's compacted in a fill. People write it two ways, so say which one you mean:

  • As a factor (the way Excav shows it): bank yards needed per compacted yard. A factor of 1.15 means it takes 1.15 bank yards to make one compacted yard.
  • As a percent of bank: how much smaller compacted is than bank. A 1.15 factor is about 13% shrinkage.
bank yards needed = compacted yards × shrink factor
compacted yards   = bank yards ÷ shrink factor

Typical ranges

These are rough ranges you'll see in published tables. Soils vary a lot from site to site. When there's a geotechnical report, use its numbers; when there isn't, use what your crews have seen on similar ground.

Material Swell (bank to loose) Shrinkage (bank to compacted)
Sand and gravel 10–15% 5–10%
Common earth, loam 20–30% 10–20%
Clay 30–40% 10–25%
Blasted rock 50–80% Rock usually doesn't shrink

Rock is the exception: even compacted, it usually takes up more room than it did in the bank.

Worked example

Made-up numbers. A site has 1,000 bank yards of cut. The material swells 30% and the shrink factor is 1.15.

Hauled, loose      1,000 × 1.30 = 1,300 LCY in the trucks
Fill it can make   1,000 ÷ 1.15 =   869.6 CCY in place

If the fill on the plans is 900 compacted yards:

Fill needs, as bank  900 × 1.15 = 1,035 BCY
Cut available                    1,000 BCY
Short                               35 BCY → import

That's a job that looked like it had extra dirt (1,000 of cut against 900 of fill) but actually needs import.

Mistakes to avoid

  • Comparing cut to fill without converting. 1,000 yards of cut doesn't fill 1,000 yards of fill.
  • Using bank yards to count trucks. Trucks carry loose yards. See how many truck loads.
  • Mixing the two shrink conventions. A 15% shrinkage and a 1.15 factor are close but not the same. Pick one and label it.
  • Forgetting the units on import. Pits often sell by the ton. Convert with the pit's density, not a guess.

Run your own numbers in the shrink and swell calculator.