  3. How to take off a pavement section: asphalt, base and pit run to tons

How to take off a pavement section: asphalt, base and pit run to tons

The Excav team · Updated

A pavement section is a stack of layers under the finished surface: asphalt or concrete on top, then crushed base, then often a subbase like pit run, sitting on prepared subgrade. Taking it off means turning one paved area on the plan into a quantity for each layer, and figuring how much dirt comes out to make room for it.

Read the typical section

Find the typical section for each kind of paving: parking lots, drive aisles, heavy duty areas and roads often differ. For each one, note:

  • the thickness of each layer, in inches;
  • whether the base extends past the edge of pavement or behind the curb;
  • the subgrade preparation (scarify and compact, geotextile, and so on).

Step 1: Measure the area

Measure each paved area at the sheet's calibrated scale, in square feet. Keep each section type as its own area.

Step 2: Yards for each layer

CY = area (SF) × depth (in) ÷ 12 ÷ 27

Step 3: Tons

Aggregate is usually bought by the ton. Multiply cubic yards by the material's density in tons per cubic yard. Get the density from your supplier for the exact material, compacted in place. It varies by pit and gradation.

For asphalt, a common rule of thumb is about 110 pounds per square yard per inch of compacted thickness:

asphalt tons = area (SY) × thickness (in) × 110 ÷ 2,000

Worked example

Made-up numbers. A 10,000 SF parking lot with 3" asphalt over 6" crushed base over 12" pit run. Densities are made up; use your supplier's.

Asphalt   10,000 ÷ 9 = 1,111.1 SY
          1,111.1 × 3 × 110 ÷ 2,000          = 183.3 TON

Base 6"   10,000 × 6/12 ÷ 27  = 185.2 CY
          185.2 × 1.48 T/CY                  = 274.1 TON

Pit run   10,000 × 12/12 ÷ 27 = 370.4 CY
          370.4 × 1.45 T/CY                  = 537.0 TON

Box out   21" total section
          10,000 × 21/12 ÷ 27                = 648.1 CY below finished grade

The box out matters for the earthwork. The proposed contours show finished grade, but the dirt work stops at subgrade, 21 inches lower here. If you figure cut and fill to finished grade, you'll be short 648 yards of excavation on this lot alone.

Things that get missed

  • Base past the edge. Many sections carry the base a foot or more past the edge of pavement or behind the curb. Add it.
  • Different sections in one lot. Heavy duty drive aisles and light duty parking stalls usually have different depths.
  • Compaction and waste. Loose material delivered compacts in place. Ask the supplier whether their density is loose or compacted, and carry a little waste.
  • Concrete areas. Sidewalks and pads have their own base depth, often thinner.

Run a layer in the aggregate tons calculator, or see how the box out feeds the cut and fill calculation.

Do this from your own plans

Excav traces the contours, figures the yards and tons, and shows the cut and fill in 3D, built from the PDFs you already get. Try it on the sample job.