The cut and fill calculation, step by step

Every yard in Excav traces back to a line you drew on the plans. No black box: plain arithmetic you can check by hand.

Four layers

From the sheet to the truck count

  1. QuantitiesFacts from the plans. Areas, lengths and counts measured at each sheet’s calibrated scale.
  2. SurfacesExisting and proposed ground built from the contours and spot grades you trace. Past the last proposed line, the grade ties back into existing ground. It never invents cut.
  3. EarthworkCut and fill compared cell by cell. Pavement sections taken off to subgrade. Bank, compacted and loose yards with your shrink and swell.
  4. HaulingImport or export in bank yards, loose yards hauled, and loads for the truck you pick.
Example, made-up numbers

Cut, bank                       1,240 CY
Fill, compacted                   860 CY
Fill as bank    860 × 1.15 shrink  =   989 CY
Export, bank    1,240 − 989        =   251 CY
Hauled, loose   251 × 1.25 swell   =   314 CY
Loads           314 ÷ 14 CY        =    23

Pavement section, 10,000 SF
Base 4"   10,000 × 4/12 ÷ 27  =  123.5 CY
          123.5 × 1.48 T/CY   =  182.7 TON

Shrink, swell and densities are yours, set once and shown next to every result.

1. Calibrate each sheet

Every sheet is calibrated to its own scale before anything is measured, so a plan at 1" = 40' and a detail at 1" = 10' in the same set both measure true. Areas, lengths and counts are facts from the plans at that scale.

2. Build existing and proposed ground

You trace the existing contours and the proposed contours and spot grades on the grading sheets. Excav builds an existing surface and a proposed surface from those lines. Where the proposed design ends, the grade ties back into existing ground instead of carrying the last contour across the site, so the volumes only come from work the plans show.

3. Compare the surfaces cell by cell

The job is split into small cells. In each one, Excav compares proposed to existing. Where proposed is lower, that cell is cut; where it is higher, it is fill. Depth times cell area gives the volume, and the cells add up to the cut and fill totals. The 3D model is the same comparison drawn: red is cut, blue is fill.

cell volume (CF) = cell area (SF) × (proposed − existing) (FT)
cut  = sum of cells where proposed is below existing
fill = sum of cells where proposed is above existing
CY   = CF ÷ 27

4. Take pavement sections off to subgrade

Where an area has a pavement section, the dirt is figured to subgrade: finished grade minus the section depth. The asphalt, base and pit run become their own line items in yards and tons, using the densities you set.

5. Convert bank, compacted and loose yards

Cut comes out of the ground in bank yards. Fill goes back in as compacted yards. To see whether the site balances, compacted fill is converted back to bank yards with your shrink factor. Anything left over is import or export. Hauling is figured in loose yards with your swell factor, then divided by the truck you pick.

Read more in shrink and swell factors explained, or try the shrink and swell calculator.

Why it can differ from the engineer’s number

Areas and lengths measured at scale match what is drawn. Earthwork totals can differ from a printed engineer’s estimate for honest reasons: where the grading is assumed to stop, whether pavement sections are taken off, and which shrink and swell factors are used. Excav shows each of those, so when the numbers differ you can see why and decide.

Paving sections

Every layer, every ton.

Set the depths. Yards and tons follow.

Heavy duty paved area with asphalt, crushed base and pit run depths, cubic yards and tons
Questions

About the calculation

What is the difference between bank, loose and compacted yards?

Bank yards are dirt as it sits in the ground. Dig it up and it swells, so it takes up more room in a truck: loose yards. Place and compact it and it ends up tighter than it started: compacted yards. Excav keeps cut in bank yards, fill in compacted yards, and converts with your swell and shrink factors so the two can be compared.

Why does the grade tie back into existing ground past the last proposed line?

Because that is where the design stops. Carrying the last proposed contour across the rest of the site would invent cut or fill nobody drew. Excav blends the proposed surface back to existing ground beyond your last proposed line, so volumes only come from work the plans show.

Where do the shrink and swell factors come from?

From you. Use the geotechnical report when there is one, or the numbers your crews have seen on similar ground. Excav shows the factors next to every result so nobody has to guess which ones were used.

Can I check the math by hand?

Yes. Every result shows the inputs that made it: the measured area, the depths, the factors and the truck size. The worked example on this page is the same arithmetic.

Does pavement come off the cut?

Yes. When an area has a pavement section, the dirt is figured to subgrade, the bottom of the section, not to finished grade. The asphalt, base and pit run are taken off as their own quantities in yards and tons.

Related: How to calculate cut and fill from contour lines · Pavement section takeoff · Truck load calculator