How many truck loads? Hauling import and export

The Excav team · Updated

Once you know whether the site is long or short on dirt, the next question is how many trucks it takes to fix it. That number drives trucking cost, which is often one of the biggest lines in a dirt bid.

Step 1: Start from bank yards

Get the import or export in bank yards, after converting fill with your shrink factor. See shrink and swell factors.

Step 2: Convert to loose yards

Trucks carry loose material.

loose yards = bank yards × swell factor

Step 3: Divide by what the truck carries

loads = loose yards ÷ yards per load   (round up)

Step 4: Check the weight

A truck can run out of legal weight before it runs out of room, especially with wet clay or rock. Figure what a full box weighs:

tons per load = yards per load × tons per loose yard

If that's over the truck's legal payload, the truck is weight-limited:

yards per load = legal payload (tons) ÷ tons per loose yard

Legal payloads depend on the truck, its axles and your state's rules. Use your own trucks' numbers.

Worked example

Made-up numbers. A site has 251 bank yards of export. Swell is 1.25. The trucks carry 14 loose yards.

Loose     251 × 1.25    = 313.75 LCY
Loads     313.75 ÷ 14   = 22.4  → 23 loads

Now the weight check. The material weighs 1.4 tons per loose yard and the trucks are good for 15 tons:

Full box  14 × 1.4      = 19.6 TON  (over 15)
Per load  15 ÷ 1.4      = 10.7 LCY
Loads     313.75 ÷ 10.7 = 29.3  → 30 loads

Seven more loads than the volume alone said, a 30% miss on trucking.

How many trucks?

Loads per truck per day comes from the cycle time: load, haul, dump and return.

loads per truck per day = working minutes ÷ cycle minutes

Made-up numbers: a 40-minute cycle in a 9-hour day is 540 ÷ 40 = 13.5, so 13 loads per truck. Thirty loads is most of a day for three trucks, or a little over a day for two.

Import is bought by the ton

For import, the pit usually sells by the ton. Convert the bank yards you need into tons with the pit's density for that material, and haul in loose yards like above.

Run your own numbers in the truck load calculator.

Do this from your own plans

Excav traces the contours, figures the yards and tons, and shows the cut and fill in 3D, built from the PDFs you already get. Try it on the sample job.