Pond and detention volume from contours

The Excav team · Updated

To find a pond's volume from the grading plan, measure the area inside each contour, then add up the volume between each pair. The conic method uses V = h ÷ 3 × (A1 + A2 + √(A1 × A2)). Two contours 2 ft apart with 10,000 SF and 14,400 SF hold 2 ÷ 3 × (10,000 + 14,400 + 12,000) = 24,267 CF, or about 899 CY.

Run your numbers

Enter each contour’s elevation and the area inside it. You get the storage at each stage and the total in cubic feet, cubic yards and acre-feet.

Open the pond volume calculator →

Storage isn't excavation

This catches people. The storage volume is the water the pond holds below each elevation: what the engineer's drainage report cares about. The excavation is the dirt you dig: existing ground minus the finished pond surface. They're only the same if the existing ground was flat at the top of the pond. Most ponds are partly dug and partly bermed, so the bid needs both the cut and the berm fill.

Use the storage number to check the plans against the drainage report. Use a cut and fill comparison of existing and proposed ground for the dirt.

Measuring the contour areas

On the grading plan, trace the inside of each proposed contour of the pond as a closed shape and measure its area at the sheet's scale. Start at the bottom (the pond floor or the outlet invert) and go up to the top of the berm or the emergency spillway. Each area is everything inside that contour, not just the ring between it and the next one.

Two methods

conic (frustum)   V = h ÷ 3 × (A1 + A2 + √(A1 × A2))
average end area  V = h × (A1 + A2) ÷ 2

h is the vertical distance between the two contours. The conic method treats each layer like a slice of a cone and is the usual choice in stormwater manuals. Average end area runs slightly higher. With contours a foot or two apart, the two are within a percent or so.

Worked example

Made-up numbers. A detention pond with these areas inside the contours:

Elevation Area (SF)
100 10,000
102 14,400
104 19,600
106 25,600
100–102  2 ÷ 3 × (10,000 + 14,400 + 12,000) = 24,267 CF
102–104  2 ÷ 3 × (14,400 + 19,600 + 16,800) = 33,867 CF
104–106  2 ÷ 3 × (19,600 + 25,600 + 22,400) = 45,067 CF

Total to 106   103,200 CF = 3,822 CY = 2.37 acre-feet
By average end area        103,600 CF

Adding up as you go gives the stage-storage table: the storage at 102 is 24,267 CF, at 104 it's 58,133 CF, at 106 it's 103,200 CF. That's the table the drainage report compares against.

Wet ponds

A retention pond with a permanent pool has two volumes: the pool below the outlet, which always holds water, and the detention storage above it. If the report's numbers are for detention only, start your table at the outlet elevation.

Common mistakes

  • Using storage as the excavation. Compare existing and proposed ground for the dirt.
  • Measuring the ring, not the inside. Each area is everything inside the contour.
  • Top area × depth. That's a box, not a pond. It can overstate the volume by half.
  • Forgetting the berm. Berms are fill, often with their own compaction spec.
  • Missing the outlet structure and forebay. They change the bottom and the cut.

Questions

How many cubic feet in an acre-foot?

43,560. An acre-foot is one acre covered one foot deep. Divide cubic feet by 43,560 to get acre-feet.

Which method should I use, conic or average end area?

Use the one the drainage report uses, so your numbers compare. Most stormwater manuals use the conic (frustum) method. With contours close together, the two are within about a percent.

Is pond storage the same as the excavation?

Only if the existing ground was flat at the top of the pond. Usually it isn't. Figure the dirt from a comparison of existing and proposed ground.

Estimates for planning and bidding. Check against your plans, specs and engineer.