The average end area method finds the volume between two cross sections by averaging their areas and multiplying by the distance between them: V = L × (A1 + A2) ÷ 2, then ÷ 27 for cubic yards. Two sections 50 ft apart with 60 SF and 40 SF of cut hold 50 × (60 + 40) ÷ 2 = 2,500 CF, or 92.6 CY.
Enter the station and the cut and fill area at each cross section. You get the volume between each pair and the totals.
Where the sections come from
Road and channel plans usually include cross section sheets every 25 or 50 feet, with the existing ground and the proposed template drawn at each station. The cut area is where existing ground is above the template; the fill area is where it's below. Some sheets print the areas; when they don't, you measure them.
With no section sheets, you can draw your own from the contours: pick stations along the centerline, read the existing and proposed elevations across the road at each one, and plot them. It's slow, which is why surface methods exist (more on that below).
Cut and fill separately
Most sections have some of each, so carry two areas per station and two volumes per segment. Never net them on the section: a section with 40 SF of cut and 30 SF of fill isn't "10 SF of cut," it's dirt dug on one side and placed on the other.
Stations
Stations count distance along the alignment in hundreds of feet. 10+50 is 1,050 ft; 12+00 is 1,200 ft. The length between two sections is the difference: 12+00 − 10+50 = 150 ft. See plan scales and stations.
Worked example
Made-up numbers. Four sections along a road:
| Station | Cut (SF) | Fill (SF) |
|---|---|---|
| 10+00 | 0 | 0 |
| 10+50 | 60 | 10 |
| 11+00 | 40 | 30 |
| 12+00 | 0 | 50 |
10+00 to 10+50 50 × (0 + 60) ÷ 2 = 1,500 CF cut 50 × (0 + 10) ÷ 2 = 250 CF fill
10+50 to 11+00 50 × (60 + 40) ÷ 2 = 2,500 CF cut 50 × (10 + 30) ÷ 2 = 1,000 CF fill
11+00 to 12+00 100 × (40 + 0) ÷ 2 = 2,000 CF cut 100 × (30 + 50) ÷ 2 = 4,000 CF fill
Cut 6,000 CF ÷ 27 = 222.2 CY (bank)
Fill 5,250 CF ÷ 27 = 194.4 CY (compacted)
Before deciding the job balances, convert the fill to bank yards with your shrink factor. See shrink and swell factors.
When average end area runs high
Averaging the two ends assumes the shape changes evenly from one to the other. When it doesn't, such as a cut that narrows to a point, average end area overstates the volume. The prismoidal formula corrects it when you know the area of a section halfway between:
V = L ÷ 6 × (A1 + 4 × Am + A2)
Example: ends of 100 SF and 300 SF, 100 ft apart, with 175 SF in the middle. Average end area gives 740.7 CY; prismoidal gives 679.0 CY, about 9% less. With sections close together and shapes that change gradually, the difference is small, which is why most specifications pay by average end area.
Where cut turns to fill
If one section is all cut and the next is all fill, averaging the two counts both across the whole distance and overstates each. Add a section at the point where the road passes from cut to fill (where the cut and fill areas are zero), and the problem goes away.
Spacing
Sections every 50 ft are fine on a straight, even road. Add sections at curves, intersections, driveways, culverts and anywhere the ground changes sharply. A missed swale between two sections is missed dirt.
Where sections fall short
Sections work well on long, narrow work like roads, ditches and channels. On a building pad or a parking lot there's no centerline to section along. Those are better done by comparing existing and proposed surfaces over the whole area: see cut and fill from contour lines.
Common mistakes
- Netting cut and fill on the section. Carry both.
- Reading the station wrong. 10+50 to 11+00 is 50 ft, not 0.5 or 150.
- Mixing section areas in SF with lengths in stations. Convert stations to feet first.
- Comparing bank cut to compacted fill. Convert with shrink first.
- Too few sections through changes. The method only knows what's at the stations.
Questions
Is average end area accurate enough to bid?
For roads and channels with sections at 25 to 50 ft, yes. It's the method most highway specifications use for pay quantities. It runs slightly high where sections change shape sharply.
What is the prismoidal formula?
V = L ÷ 6 × (A1 + 4 × Am + A2), where Am is the area of a section halfway between the two ends. It's exact for shapes that change smoothly and corrects average end area's overestimate.
How do I get cross section areas from a PDF?
If the section sheets print them, use those. If not, measure the area between the existing ground line and the proposed template on each section, at that sheet's scale.
Estimates for planning and bidding. Check against your plans, specs and engineer.