Cut
222.2CY
- Fill
- 194.4 CY
- Cut over fill
- 27.8 CY
- Length
- 200 ft
Neat volumes between sections. Apply shrink and swell before comparing cut to fill.
| From | To | Length (ft) | Cut (CY) | Fill (CY) |
|---|---|---|---|---|
| 10+00.00 | 10+50.00 | 50.0 | 55.6 | 9.3 |
| 10+50.00 | 11+00.00 | 50.0 | 92.6 | 37.0 |
| 11+00.00 | 12+00.00 | 100.0 | 74.1 | 148.1 |
How this is calculated
The formula
length = next station − this station CY = length × (A1 + A2) ÷ 2 ÷ 27 (cut and fill separately) prismoidal, with a middle section: L ÷ 6 × (A1 + 4·Am + A2) ÷ 27
Assumptions you can change
Stations are sorted for you. Average end area runs a little high where the sections change shape sharply; the prismoidal formula corrects that if you have a middle section.
With your numbers
10+00.00–10+50.00: 50.0 × (0 + 60) ÷ 2 ÷ 27 = 55.6 CY cut10+50.00–11+00.00: 50.0 × (60 + 40) ÷ 2 ÷ 27 = 92.6 CY cut11+00.00–12+00.00: 100.0 × (40 + 0) ÷ 2 ÷ 27 = 74.1 CY cuttotal: 222.2 CY cut, 194.4 CY fill
The why behind it, with a worked example: The average end area method for cut and fill →
Sources and method
- Average end area: V = L × (A1 + A2) ÷ 2, used in most highway earthwork specifications.
- Prismoidal formula, when a middle section is known: V = L ÷ 6 × (A1 + 4·Am + A2). Average end area runs high where sections change sharply.
Estimates for planning and bidding. Check against your plans, specs and engineer.