Average end area calculator

Enter the station and the cut and fill area at each cross section. You get the volume between each pair and the totals.

Cross sections, in station order
StationCut area (SF)Fill area (SF)Remove

Areas come from each cross section sheet (or the area you measure between existing and proposed lines on it). Leave a box blank for zero.

Cut
222.2CY
Fill
194.4 CY
Cut over fill
27.8 CY
Length
200 ft

Neat volumes between sections. Apply shrink and swell before comparing cut to fill.

Volume between each pair of sections
FromToLength (ft)Cut (CY)Fill (CY)
10+00.0010+50.0050.055.69.3
10+50.0011+00.0050.092.637.0
11+00.0012+00.00100.074.1148.1

How this is calculated

The formula

length = next station − this station
CY     = length × (A1 + A2) ÷ 2 ÷ 27       (cut and fill separately)
prismoidal, with a middle section: L ÷ 6 × (A1 + 4·Am + A2) ÷ 27

Assumptions you can change

Stations are sorted for you. Average end area runs a little high where the sections change shape sharply; the prismoidal formula corrects that if you have a middle section.

With your numbers

  1. 10+00.00–10+50.00: 50.0 × (0 + 60) ÷ 2 ÷ 27 = 55.6 CY cut
  2. 10+50.00–11+00.00: 50.0 × (60 + 40) ÷ 2 ÷ 27 = 92.6 CY cut
  3. 11+00.00–12+00.00: 100.0 × (40 + 0) ÷ 2 ÷ 27 = 74.1 CY cut
  4. total: 222.2 CY cut, 194.4 CY fill

The why behind it, with a worked example: The average end area method for cut and fill →

Sources and method
  • Average end area: V = L × (A1 + A2) ÷ 2, used in most highway earthwork specifications.
  • Prismoidal formula, when a middle section is known: V = L ÷ 6 × (A1 + 4·Am + A2). Average end area runs high where sections change sharply.

Estimates for planning and bidding. Check against your plans, specs and engineer.