Pond volume calculator

Enter each contour’s elevation and the area inside it. You get the storage at each stage and the total in cubic feet, cubic yards and acre-feet.

Contours, bottom to top
Elevation (ft)Area inside the contour (SF)Remove
Method

Measure the area inside each contour on the grading plan. The bottom contour is the pond bottom or the outlet invert.

Storage to the top contour
3,822.2CY
Cubic feet
103,200 CF
Acre-feet
2.369 AF
By average end area
103,600 CF
Stage-storage
Elevation (ft)Area (SF)Layer (CF)Storage (CF)Storage (AF)
100.0010,000000.000
102.0014,40024,26724,2670.557
104.0019,60033,86758,1331.335
106.0025,60045,067103,2002.369

How this is calculated

The formula

conic (frustum): V = h ÷ 3 × (A1 + A2 + √(A1 × A2))
average end area: V = h × (A1 + A2) ÷ 2
CY = CF ÷ 27      acre-feet = CF ÷ 43,560

Assumptions you can change

This is storage below each elevation. The excavation to build the pond also depends on the existing ground around it.

With your numbers

  1. 100.00–102.00: 2.00 ÷ 3 × (10,000 + 14,400 + 12,000) = 24,267 CF
  2. 102.00–104.00: 2.00 ÷ 3 × (14,400 + 19,600 + 16,800) = 33,867 CF
  3. 104.00–106.00: 2.00 ÷ 3 × (19,600 + 25,600 + 22,400) = 45,067 CF
  4. total 103,200 CF ÷ 27 = 3,822.2 CY

The why behind it, with a worked example: Pond and detention volume from contours →

Sources and method
  • Conic (frustum) method: V = h ÷ 3 × (A1 + A2 + √(A1·A2)). Average end area: V = h × (A1 + A2) ÷ 2. Both are standard for stage-storage in stormwater design manuals.
  • Storage is the volume below each elevation, not the excavation. Excavation also depends on the ground around the pond.

Estimates for planning and bidding. Check against your plans, specs and engineer.