Storage to the top contour
3,822.2CY
- Cubic feet
- 103,200 CF
- Acre-feet
- 2.369 AF
- By average end area
- 103,600 CF
| Elevation (ft) | Area (SF) | Layer (CF) | Storage (CF) | Storage (AF) |
|---|---|---|---|---|
| 100.00 | 10,000 | 0 | 0 | 0.000 |
| 102.00 | 14,400 | 24,267 | 24,267 | 0.557 |
| 104.00 | 19,600 | 33,867 | 58,133 | 1.335 |
| 106.00 | 25,600 | 45,067 | 103,200 | 2.369 |
How this is calculated
The formula
conic (frustum): V = h ÷ 3 × (A1 + A2 + √(A1 × A2)) average end area: V = h × (A1 + A2) ÷ 2 CY = CF ÷ 27 acre-feet = CF ÷ 43,560
Assumptions you can change
This is storage below each elevation. The excavation to build the pond also depends on the existing ground around it.
With your numbers
100.00–102.00: 2.00 ÷ 3 × (10,000 + 14,400 + 12,000) = 24,267 CF102.00–104.00: 2.00 ÷ 3 × (14,400 + 19,600 + 16,800) = 33,867 CF104.00–106.00: 2.00 ÷ 3 × (19,600 + 25,600 + 22,400) = 45,067 CFtotal 103,200 CF ÷ 27 = 3,822.2 CY
The why behind it, with a worked example: Pond and detention volume from contours →
Sources and method
- Conic (frustum) method: V = h ÷ 3 × (A1 + A2 + √(A1·A2)). Average end area: V = h × (A1 + A2) ÷ 2. Both are standard for stage-storage in stormwater design manuals.
- Storage is the volume below each elevation, not the excavation. Excavation also depends on the ground around the pond.
Estimates for planning and bidding. Check against your plans, specs and engineer.